Project Description:
The Yorba Linda Water District (YLWD) owns and maintains existing 8-inch waterlines that are located within Via Del Agua, Via Del Puente, and Via Del Cerro in the City of Yorba Linda which have been prioritized for replacement this winter. This project will enhance fire flow reliability in the area to align with YLWD’s commitment to providing reliable water services to protect public health and the environment.
Project Location: Via Del Agua, Via Del Puente, and Via Del Cerro, Yorba Linda, CA
Project Status: Completed May 2025
Project Name: Waterline Replacement Project in the City of Yorba Linda (Copper Canyon Road & Ave De Michele)
Project Description:
The Yorba Linda Water District (YLWD) owns and maintains existing 16-inch and 24-inch water transmission lines that are located within Copper Canyon Road and Ave De Michele in the City of Yorba Linda which have been prioritized for rehabilitation. This completed project extends the useful life and improves reliability in the area to align with YLWD’s commitment to providing reliable water services to protect public health and the environment.
Project Location: Copper Canyon Road & Ave De Michele, Yorba Linda, CA
Project Status: Completed May 2025
Project Description:
1,150-feet of existing 6-inch aged waterlines located in the City of Placentia will be replaced with larger diameter pipes and relocated from the parkway to the middle of the street in the winter of 2025. This project will enhance fire flow reliability in the area.
Project Location: McKenzie Drive, Lute Avenue, Roxborough Drive, and Cedarlawn Drive, in the City of Placentia, CA
Project Status: Completed April 2025
Project Description:
The Yorba Linda Water District (YLWD) owns and maintains existing 6-inch waterlines that are located within Mandarin Ln. in the City of Yorba Linda which have been prioritized for replacement this winter. This project will enhance fire flow reliability in the area to align with YLWD’s commitment to providing reliable water services to protect public health and the environment.
Project Location: Mandarin Ln., Yorba Linda, CA
Project Status: Completed April 2025

Project Description:
As part of the District’s continuing Rehabilitation &
Replacement (R&R) Program to replace aging infrastructure, four Pressure Regulating Stations (PRSs) will be replaced, and two PRSs will be abandoned.
Project Location: Various Locations
Project Status: Completed March 2025
Project Description:
Approximately 2,315 linear feet of Ductile Iron Pipes in high-pressure areas and with a history of leaks have been prioritized for Phase 1.
Project Location: Camino De Bryant Area
Projected Status: Completed
Project Description:
The existing sewer near Main Street in Downtown Yorba Linda was in very poor condition and could not be adequately cleaned or monitored by the District, and was not compliant with pipe size standards. The project included the replacement of 465 linear feet of 6-inch sewer with 8-inch sewer line. The District utilized a combination of open trench and pipe bursting. Perpetual construction easements and access licenses were acquired from the City of Yorba Linda for constructing and maintaining the replacement sewer.
Project Location: Main Street, Yorba Linda, CA
Project Status: Completed
Project Description:
The project is part of the District’s continuing
Rehabilitation & Replacement (R&R) Program to replace aging infrastructure. The Operations and Engineering Departments work together to identify sewer lines requiring rehabilitation/replacement. 6,500 linear feet of sewer mains and 12 manholes have been identified for FY23-24 for lining that will be cast and cured in place.
Project Location: Sewer lines throughout the District
Project Status: Completed
Project Description:
Well 5 will be rehabilitated to extend its life and improve efficiency. This may require the replacement
of parts and lowering the pump bowl.
Project Location: YLWD Headquarters
Project Status: Completed
Project Description:
Well 19 will be rehabilitated. This project will be completed in two phases.
Project Location: YLWD Headquarters
Project Status: Completed